- A study is being conducted to carry out Environment and Social Impact Assessment in connection with Haryana Orbital Rail Corridor from Palwal to Sonipat including connections to the existing Railway Network.
- Letter Of Acceptance for ESIA issued to M/s Overseas Min-Tech Consultants on 17-Nov-2020.
- ESIA consultant visited HORC section with AIIB Team on 19-Nov-2020.
- A meeting was conducted by HRIDC with ESIA consultant on 20- Nov-2020. Following documents were collected by consultant from HRIDC office:-
- Detailed Project Report (DPR)
- KML files of project alignment
- Land Acquisition Plan (LAP)
- Environmental and Social Screening Report
- A reconnaissance survey tour from 23-Nov-2020 to 24-Nov-2020 was conducted by ESIA consultant to identify sensitive locations for environmental monitoring (Air, Noise, Water, Soil and Vibration).
- ESIA has submitted Final Inception Report 02-Dec-2020.
- Stakeholder consultations have been planned from 14-Dec-2020 to 05-Jan-2021